Case study
Laying foundations for vital carbon capture power station
North Lincolnshire, UK
Client
SSE Thermal
Project duration
22 August 2022 - 07 March 2023
SSE Thermal selected Fugro to undertake a geotechnical ground investigation and engineering analysis for Keadby 3, which it is developing with Equinor. The proposed plant could be one of the UK’s first flexible power stations equipped with carbon capture technology. We delivered Geo-data to enable SSE Thermal to understand the soil conditions, reveal the ground risks in the early stages, and make informed decisions during later phases of this proposed development.
Planning, feasibility, conceptual design
Design
Construction
Operations and maintenance
Decommissioning
Show full process
Challenge
Due to the location of the site, part of the planning process included flood risk mapping as we needed to raise ground levels to 2.8 m above sea level for this project. This was important because the expected conditions could cause soil settlement. Soil settlement can affect foundations and require a lot of work to fix in the future.
SSE Thermal required detailed and reliable Geo-data to understand the properties of soils and ground conditions to make informed decisions in the engineering, design and construction phases of the power station’s development. Accurate geological data is crucial for construction projects such as Keadby 3. This data helps to identify ground conditions early on, which can save money and ensure stable foundations.
The entire ground investigation process was an exceptionally collaborative approach between Fugro and SSE Thermal to respond to the site requirements as soon as information was gathered.
The original scope of investigation required a range of our services including:
Cable percussion boreholes with rotary follow on
Dynamic sampling boreholes
Plate bearing tests
Cone penetration testing (CPT)
Inspection pits with geotechnical site investigation and environmental sampling
Geotechnical and environmental testing
Geotechnical laboratory testing
Factual and interpretive reporting
Geotechnical engineers on site at Keadby 3 power station
Solution
The wide range of Geo-data acquired allowed us to react quickly to any issues encountered onsite, advising SSE Thermal on the most effective and cost effective way forward. Utilising our breadth of in-house services, the ground investigation was able to be adapted and customised in real time, providing our client with flexibility and quick response times. This meant that they could keep on track with their programme of delivery without having to sacrifice the quality of data.
Data consultancy supported approach
Fugro provided a variety of geo consulting services during this ground investigation, collaborating with SSE Thermal and their major stakeholders. This included:
Optimising the scope of the investigation
Schedule-appropriate laboratory testing regimes
Provided early analysis with separate interim reports to help progress design earlier
Geo environmental assessment to provide a conceptual site model and recommendations for potential remediation requirement
An interpretative report which updated the information in the interim reports regarding settlement analysis for the placement of the engineered fill, foundation design (shallow and deep), and pavement design
1 / 2
Screenshot - Fugro’s 3D ground model of the Keadby 3 site
3D ground modelling and visualisation
As our partnership developed, the scope grew, and we provided SSE Thermal with interpretative geotechnical and geo-environmental reporting and ground modelling services. This included a comprehensive set of factual ground data, derived and measured ground parameters on conclusion of the field and laboratory testing, and post field work monitoring.
Alongside valuable interim reporting, geological mapping and a 3D ground model provided a powerful visual aid for SSE Thermal to assess the site. It allowed for displaying and interpreting the complex data and SSE Thermal found the ground conditions to be better than expected.
Key metrics
cone penetration tests completed
standard penetration tests undertaken
laboratory soil and rock tests performed
Interim Reporting
To ensure constant and consistent communication with our client, three interim reports were provided to SSE Thermal over the duration of the investigation at Keadby 3. These summarised:
The impact of the placement of the engineered fill
Shallow foundation and road design parameters
Pile design for heavily loaded structures, including rock socketed piles, aided by our 3D ground model
Whilst interim reports are included in some projects, the three interim reporting approach utilised at Keadby 3 was designed to ensure SSE Thermal had real-time updates which allowed them to move on to the design phase earlier and to be informed of factors including soil settlement and mechanical properties that needed to be accounted for ahead of time.
With our interim engineering analyses reports, we were able to provide project surety and reduce the overall project duration by allowing the designers to start their work earlier.
Impact
Our exceptionally collaborative approach allowed the Keadby 3 ground investigation to be delivered in a way that blended conventional and progressive methods of identifying geohazards. The 3D ground model provided early insights and a targeted approach for SSE Thermal, enabling a thorough risk assessment. This proactive risk assessment helped in mitigating potential issues and ensuring the stability and safety of the construction project.
CPT trucks ready for deployment on site
Geotechnical Investigation
Data was collected using conventional and advanced CPT testing methods, together with laboratory testing carried out on soil samples recovered from the boreholes and plate bearing tests.
In contrast to the expected ground conditions, the data revealed mostly coarse soil in the first locations, overlying the variably weathered Mercia Mudstone bedrock. Together with SSE Thermal, we modified the scope of the investigation to include more in situ testing to obtain reliable geotechnical parameters both from soil and rock. This alternative approach was needed due to the difficulty in testing coarse materials, as well as weathered rock, in the laboratory.
The use of our cone pressuremeter systems and high pressure dilatometer in the Mercia Mudstone helped to gather this information during the investigation and reduce laboratory time, while obtaining high quality in situ data. The site data was continuously transferred to SSE Thermal as it was collected so their designers were able to see the development of the site model in near real-time.
Our view
Energy transition
At Fugro, we help improve the efficiency of energy generation and minimise the impact on our environment.