Fugro completes bi-directional working pile load tests for triple deck roundabout

Pile testing by Fugro using the Osterberg Cell (O-cell®) bi-directional technique has saved time, reduced safety risks and overcome space constraints during piling for Highways England’s A19/A1058 junction improvements near Newcastle, UK.

Wallingford, UK
31 Mar 2017

A three tier interchange is being created by the construction of an underpass below the existing A19 roundabout, three new single span bridges and slip roads.

Fugro was appointed by Bauer Technologies, the foundations contractor for critical structures, to carry out static load tests to verify the piled foundation design for the north bridge, south bridge and central pier.

Speaking about the project Martin Blower, managing director of Bauer Technologies, said: “Bauer appointed Fugro to carry out pile load tests to verify the capacity of these critical foundations, as Fugro has been undertaking these test for over 20 years and is a global organisation with vast experience and capability.”

Work has been complicated by tight access to the three test locations and limited working footprint, with the busy A19 remaining open throughout the scheme. This would have proved challenging for the transportation and erection of test beams or kentledge blocks for a conventional test pile.

Fugro’s O-cell requires little or no space at the pile head during testing. The method offers a safer and more expedient alternative to traditional top down methods and performs tests in two directions, with the O-cell assembly positioned between the upper and lower pile elements.

Paul Cheesman, operations manager at Fugro, said: “O-cell load testing is a key feature of Fugro’s comprehensive services for all types of foundations. This method is ideally suited to sites with restricted access such as this, especially where there are safety concerns, because the system loads the pile within the shaft and not above ground. These three working piles were tested soon after installation with minimal disruption to the programme. Grouting the O-cells after testing enabled the working piles to be incorporated into the foundation structure.”

Piling started in December 2016 and is due to finish by the end of 2017.

Around 25% of all pile tests undertaken globally with Fugro’s bi-directional O-cell method are carried out on working piles for infrastructure works such as bridges, buildings and skyscrapers.

 

For more information

Media

Rob Luijnenburg
media@fugro.com
+31 70 31 11 129

Investors

Catrien van Buttingha Wichers
c.vanbuttingha@fugro.com
+31 70 31 15 335

 

Share this page

Sign up for email updates

Email updates